The critical path for a project was found to be 37 days. The variances total 27. What is probability of completing in 43 days? Below is information that might be useful to answer the question. Answer to 2 decimal points

Answers

Answer 1

Answer:

0.1241.

Step-by-step explanation:

So, from the question we are given the following parameters or information or data which are going to help us in solving this particular question/problem. They are; [1]. The critical path for a project = 37 days, the variances total or variance of critical path or sum of variance on critical path]². = 27, the desired completion time/day = 43 days.

So, we will be making use of the formula given below;

The number of standard deviation = desired completion time/day - critical time or sum of critical path times ÷√[variance of critical path or sum of variance on critical path]².

The number of standard deviation = 43 - 37 ÷ √27 = 1.1547.

Thus, the probability of completing in 43 days = P(Z > 1.1547) = 0.1241.


Related Questions

(9x+5)+(-2x^2+10x)
(9x+5)+(−2x
2
+10x)

Answers

Answer:

If i´m correct and read the answer correct it should be:

-18x³+80x²+65x+5

Step-by-step explanation:

Hopefully this is correct, I couldn't understand if (-2x 2+10x) was spaced or if it was being multiplied.

Question 1 (2 points)
Bentley is trying to get better at skateboarding. He has a goal of skateboarding 5 miles total this week with two short runs and one longer run. His two short runs total 2.25 miles. How long will his long skateboard run need to be in order to hit his goal?

To find the length of Bentley’s long run, you would use:

5 – 2.25

Question 1 options:
True
False

Answers

Answer:

True

Step-by-step explanation:

If he is doing 2 short runs and one long run, and his 2 short runs equal 2.25 miles, you'd need to subtract them from the total to find out the long run.

How many years will it take for Steven to make a total of $21,200?
(7 points)
12
8
6
10

Answers

the answer would be 10

3s (s - 2) =12s, please help me this. Thank you!

Answers

Answer: s = 0, or s = 6

Answer:hbjnhbgfvrdfghjhgfdfghjhgfghjkl

Find the unknown angle measures.

Answers

Answer:

x = 9°

y = 119°

Step-by-step explanation:

Given,

y° = 61°+58° { the exterior angle formed by producing the side of triangle is equal to two non-adjacent angle}

or, y° = 119°

therefore, y° = 119°

Now,

52°+y°+x° = 180°{the sum of angle if triangle is 180°}

or, 52°+119°+x°= 180°

or, 171°+x° = 180°

or, x° = 180°-171°

or, x° = 9°

therefore, x° = 9°

if you subtract 19 from my number and multiply the difference by -2​, the result is -8

Answers

Answer:cool

Step-by-step explanation:

Answer:

23

Step-by-step explanation:

let the number be 'a'

-2(a - 19)= -8

open the brackets

-2a + 38 = -8

collect like terms

38 + 8 = 2a

46 = 2a

a = 23

Please help!!
x^2-2x+1-9y^2

Answers

Answer:

[tex]\left(x-1+3y\right)\left(x-1-3y\right)[/tex]

Step-by-step explanation:

[tex]x^2-2x+1-9y^2\\\\factor(skip for time)\\\\\left(x-1\right)^2-9y^2\\\\[/tex]

A little algebra process later...

you got the answer

Hoped this helped ya

<3

Red

Answer:

(x-1-3y) x (x-1+3y)

Step-by-step explanation:

x^2-2x+1-9y^2

Using a^2 - 2ab + b^2 = (a-b)^2 (factor the expression) = (x-1)^2 - 9y^2

(x-1)^2 - 9y^2 = (x-1-3y) x (x-1+3y)  should be the answer :)

Tickets for a drumline competition cost $5 at the gate and $3 in advance. One hundred more tickets were sold in advance than at the gate. The total revenue from ticket sales was $1990. How many tickets were sold in advance?

Answers

Answer:

The number of tickets sold at the gate is [tex] G = 211.25[/tex]

The number of tickets sold in advance is  [tex]  A = 311.25 [/tex]

Step-by-step explanation:

From the question we are told that

 The cost of a tickets at the gate is [tex]a =  \$ 5[/tex]  

  The cost of a ticket in advance is  [tex]b =  \$ 3[/tex]

Let the number of ticket sold in the gate be G

Let the number of ticket sold in advance  be   A

From the question we are told that

  One hundred more tickets were sold in advance than at the gate and this can be mathematically represented as

       [tex]G  +  100 =  A[/tex]

From the question we are told that

  The total revenue from ticket sales was $1990  and this can be mathematically represented as

    [tex]5 G  +  3A  =  1990[/tex]

substituting for  A in the equation above

    [tex]5 G  +  3[G  +  100]=  1990[/tex]    

    [tex]5 G  +  3G  +  300=  1990[/tex]    

    [tex] 8G  +  300=  1990[/tex]  

    [tex] 8G  =  1690[/tex]

=>  [tex] G = 211.25[/tex]

Substituting this for G in the above equation

     [tex]5 [211.25]  +  3A  =  1990[/tex]

=>    [tex]  3A  =  1990 - 1056.25[/tex]

=>    [tex]  A = 311.25 [/tex]

________ and ________ are two ways that substances pass through a cell membrane out of the cell. A Photosynthesis, diffusion B Diffusion, active transport C Active transport, mitosis D Photosynthesis, mitosis

Answers

Answer:

b. diffusion and active transport

Step-by-step explanation:

these are two ways that substances, like nutrients, pass through cell membranes.

Answer:

b

Step-by-step explanation:

What formula is used to
determine the expected value for a variable?

Answers

The basic expected value formula is the probability of an event multiplied by the amount of times the event happens: (P(x) * n).

function rule y=3x-3

Answers

Answer:

-15, -9, -3, 3

Step-by-step explanation:

First One:

y =3(-4)-3 is -15

Second:

y= 3(-2)-3 is -9

Third:

y= 3(0)-3 is -3

Last One:

y= 3(2)-3 is 3

Graph the line y-3=-1/3(x+2)

Answers

Slope: 1/2

y-intercept(s): (0, 7/3)

x: 0, 7

y: 7/3, 0

Step-by-step explanation:

y=-3 -1/3(1+2)=2/3.3=1.3=3

y=3

Suppose that Elsa and Frank determine confidence intervals based on the same sample proportion and sample size. Elsa uses a larger confidence level than Frank. How will midpoint and width of confidence intervals compare

Answers

Answer:

elsa's interval width will be greater than that of frank

Step-by-step explanation:

first of all we are told that both Elsa and Frank have the same sample proportion so their midpoint is also going to be the same.

now as the confidence level goes higher, so also would the margin of error increase. then the width of the confidence interval would rise so it can be more confident.

from this question elsa has a larger confidence level therefore her intervals width will be greater than franks own.

Which statement about residual plots is not true?

A. If there is an obvious pattern, the model is probably reasonable.

B. The vertical axis shows residuals.

C. The x-axis appears in the middle of the graph.

D. The sum of the residuals is 0.

Answers

Answer:

Step-by-step explanation:

d

Answer:

A

Step-by-step explanation:

Question 3 of 6 (1 point) Attempt 33 of Unlimited View question in a popup

2.4 Section Exercise 6

In a study of 550 meals served at 75 campus cafeterias, 77 had less than 10 grams of fat but not less than 350 calories; 81 had

less than 350 calories but not less than 10 grams of fat; 186 had over 350 calories and over 10 grams of fat.

Part: 0/2

E

Part 1 of 2

(a) What percentage of meals had less than 10 grams of fat? Round your answer to the nearest tenth of a percent.

of the meals studied, 1% of them had less than 10 grams of fat.

Answers

Answer:

10%

Step-by-step explanation:

(a) What percentage of meals had less than 10 grams of fat?

(b) Round your answer to the nearest tenth of a percent.

To find the percentage of meals with less than 10 grams of fat, count the number of meals with less than 10 grams of fat and divide by the total number of meals; multiply this figure by a hundred.

(A) Total number of meals = 550

Number of meals having less than 10 grams of fat = 77

Percentage of meals having less than 10 grams of fat = 77/550 × 100

= 0.14 × 100 = 14%

(B) Rounding the answer to the nearest tenth of a percent means approximating it to the nearest multiple of 10 that is not more than 100 (where 100 here represents a full cent or 'percent').

The multiples of 10 that are close to 14 are 10 and 20. The closest being 10, your answer becomes 10%

The body temperatures of a group of healthy adults have a​ bell-shaped distribution with a mean of 98.18 F and a standard deviation of 0.65 F. Using the empirical​ rule, find each approximate percentage below.

a.

What is the approximate percentage of healthy adults with body temperatures within 3 standard deviation of the​ mean, or between 96.23 F and100.3 ​F?

Answers

Answer:

99.7%

Step-by-step explanation:

Empirical rule formula states that:

• 68% of data falls within 1 standard deviation from the mean - that means between μ - σ and μ + σ.

• 95% of data falls within 2 standard deviations from the mean - between μ – 2σ and μ + 2σ.

• 99.7% of data falls within 3 standard deviations from the mean - between μ - 3σ and μ + 3σ.

From the question, we have mean of 98.18 F and a standard deviation of 0.65 F

The approximate percentage of healthy adults with body temperatures between 96.23 F and100.13 ​F is

μ - 3σ

= 98.18 - 3(0.65)

= 98.18 - 1.95

= 96.23 F

μ + 3σ.

98.18 + 3(0.65)

= 98.18 + 1.95

= 100.13 F

Therefore, the approximate percentage of healthy adults with body temperatures between 96.23 F and 100.13 ​F which is within 3 standard deviations of the mean is 99.7%

PLEASE HELP Please i don’t understand

Answers

Answer:

answer is 5

Step-by-step explanation:

f(5)= -5×5^2+26×5

= -125+130

= 5

What is the midpoint of the segments with endpoints (3,7) and (9,15)

Answers

The midpoint is (6, 11)

I have attached the equation so it’s easier to understand.

To find the midpoint we do
(x^1+x^2 /2 , y^1+y^2 /2)

3, 7 is x^1, y^1
And
9, 15 is x^2, y^2

(3+9 /2 , 7+15 /2)

Add the x and y =

(12/2 , 22/2)

Now we divide both by 2 =

(6, 11)

Answer:

(6,11)

I can confirm that this question is right.

12/2      22/2

(6   ,        11)

Rectangle A’B’C’D’ is the image of rectangle ABCD after which of the following rotations?

Answers

Answer:

You're right!

Step-by-step explanation:

Answer:

Were you right?

Step-by-step explanation:

Find the surface area of the cube shown below 2.3

Answers

Answer:

2 2/3 or 8/3

Step-by-step explanation:

Formula for each side = 2/3 x 2/3

2/3 x 2/3 = 4/9

6 sides

4/9 x 6 or 4/9 + 4/9 + 4/9 + 4/9 + 4/9 + 4/9

=2 2/3 or 8/3

Answer:

2 2/3

Is the answer

solve for z 3=(z+1) write your answers as integers or as proper or improper fractions

Answers

Answer:

z=2

Step-by-step explanation:

Just solve

1 + z = 3 (minus 1 on both sides)

z = 2

Plug in

3=(2+1)

3 = 3

What is the absolute value of 5,234?

Answers

Answer:

Step-by-step explanation:

5.234

Pls answer fast Y=Mx+b for x

Answers

Answer:

y=mx+b

y=mx+b-b

y-b=mx

y-b/m = mx/m

y-b/m = x

Answer:

x = (y - b)/M.

Step-by-step explanation:

y = Mx + b

Mx = y - b

x = (y - b)/M.

3. How many solutions are there to the
equation 2x^2 - 3x +12=0? Tell how
you know.

Answers

Answer:

If you're talking about solutions in general (real and imaginary solutions), there is 2, because the fundamental theorem of algebra says that the number of roots of any polynomial is the degree if it's highest power, which is 2.

If you're talking about only real solutions, there is 0. To show that, we can take the discriminant (b^2-4ac) part of the quadratic equation, and plug in the know values. We then get:

(-3)^2-4*2*12

=9-96

=-87

Remember, the discriminant will be taken the square root. Since this is negative, the answer will be imaginary. Therefore, there is no real solution.

PLEASE HELP
ILL GIVE BRAINLIEST

Answers

Answer:

f(7x−1)=63x−16

Step-by-step explanation:

Answer:

x=3

Step-by-step explanation:

since f(x) and g(x) are equal, we can make the equation, 9x-7 = 7x - 1

9x = 7x + 6, 2x = 6, x = 3

suppose that the life distribution of an item has the hazard rate function of what is the probability that

Answers

Answer:

that what

Step-by-step explanation:

what is the pattern 2 10 40 120

Answers

Answer:

2 plus 3

Step-by-step explanation:


Order from least to greatest:
-5/6,0.567,-0.11,-1/4

Answers

Answer:

-5/6,-1/4,-0.11,0.567

Step-by-step explanation:

A lumber supplier sells 96-inch pieces of oak. Each piece must be within ¼ of an inch of 96 inches. Write and solve an inequality to show acceptable lengths.

Answers

Answer:

[tex]95 \frac{3}{4} \: inch \leqslant x \leqslant 96 \frac{1}{4} \: inch[/tex]

Step-by-step explanation:

Given that a lumber supplier sells 96 inch Pieces of oak which must be within 1/4 of an inch.

This situation can be represented by the following absolute value inequality:

[tex]|x \: - 96| \: \leqslant \: \frac{1}{4} [/tex].

The absolute value can be thought of as the size of something because length cannot be negative. The length must be no more than 1/4 away from 96.

To simplify this, pretend this is a standard equality, |x-96| = 1/4. 1/4 is the range of acceptable length, 96 is the median of the range, and x is the size of the wood.

First apply the rule |x| = y → x = [tex]\pm[/tex]y

|x-96| = 1/4

x - 96 = [tex]\pm[/tex]1/4

x = [tex]96 \pm 1/4[/tex]

(These are just the minimum, and maximum sizes)

Now with a less than or equal to, the solutions are now everything included between these two values.

Therefore:

[tex]96 - 1/4 \: \leqslant x [/tex] [tex]\leqslant \: 96 + 1/4 [/tex]

With less than inequalities, you must have the lower value on the left, and the higher value on the right.

If x represents the size of the pieces, then the acceptable lengths are represented by this following inequality:

[tex]95 \frac{3}{4} \: inch \leqslant x \leqslant 96 \frac{1}{4} \: inch[/tex]

This is interpreted as x (being the size of the oak) is greater than or equal to 95 3/4, and less than or equal to 96 1/4 in inches.

A company sells widgets. The amount of profit, y, made by the company, is related to the selling price of each widget, x, by the given equation. Using this equation, find out what price the widgets should be sold for, to the nearest cent, for the company to make the maximum profit.
y=-10x^2+600x-3588
y=−10x
2
+600x−3588

Answers

Answer:

Step-by-step explanation:

The maximum profit will be found in the vertex of the parabola, which is what your equation is. You could do this by completing the square, but it is way easier to just solve for h and k using the following formulas:

[tex]h=\frac{-b}{2a}[/tex] for the x coordinate of the vertex, and

[tex]k=c-\frac{b^2}{4a}[/tex] for the y coordinate of the vertex.

x will be the selling price of each widget and y will be the profit. Usually, x is the number of the items sold, but I'm going off your info here for what the vertex means in the context of this problem.

Our variables for the quadratic are as follows:

a = -10

b = 600

c = -3588. Therefore,

[tex]h=\frac{-600}{2(-10)}=30[/tex] so the cost of each widget is $30. Now for the profit:

[tex]k=-3588-(\frac{(600)^2}{4(-10)})[/tex] This one is worth the simplification step by step:

[tex]k=-3588-(\frac{360000}{-40})[/tex] and

k = -3588 - (-9000) and

k = -3588 + 9000 so

k = 5412

That means that the profit made by selling the widgets at $30 apiece is $5412.

Hence,the profit made by selling the widgets at $[tex]30[/tex] apiece is $[tex]5412[/tex].

What is the maximum profit?

Maximum profit, or profit maximisation, is the process of finding the right price for your products or services to produce the best profit.

Here given that,

A company sells widgets. The amount of profit, [tex]y[/tex], made by the company, is related to the selling price of each widget, [tex]x[/tex], by the given equation.

As the maximum profit found in the vertex of the parabola,

Here, [tex]x[/tex] will be the selling price of each widget and [tex]y[/tex] will be the profit.

The number of items sold is [tex]x[/tex].

So, the quadratic equation is:-

[tex]a = -10b = 600c = -3588.[/tex]

Therefore, so the cost of each widget is $[tex]30[/tex].

For the profit:-

[tex]k = -3588 - (-9000) andk = -3588 + 9000 sok = 5412[/tex]

Hence,the profit made by selling the widgets at $[tex]30[/tex] apiece is $[tex]5412[/tex].

To know more about the maximum profit

https://brainly.com/question/16755335

#SPJ2

Other Questions
There are approximately 7.5 10 18 grains of sand on Earth. There are approximately 7 10 27 atoms in an average human body. Are there more grains of sand on Earth or atoms in an average human body? How do you know? 1.2Is media a curse or a blessing? Explain. The frequency vibrations for a certain guitar string When is blood can be determined by the equation below, Where F is the number of vibration per second and T is measured in pounds.If the frequency of the vibrations is 600 vibrations per second, How many pounds of tantrums was used to plug the string? F = 200sqrt(T) 1. Winston Churchill's suggestion to kill the leaders of the Nazi Party by firingsquad without a trial is an example ofA. genocideB. rule of lawC. rule of forceD. rehabilitationChurchill's suggestion? * What do you think the biggest obstacle was in Native American and US Government relations? Match each quantity in the first list with an appropriate unit of measurement from the second list. g 1. The volume of a refrigerator2. Distance a person can run in 10 minutes3. The surface area of a tissue box4. The perimeter of a baseball field5. The surface area of the moon6. The volume of a large lake 7. The length of macaroni noodle8. The area of a bed sheeta. cubic kilometersb. square inchesc. metersd. square kilometers e. centimeterf. mileg. cubic feeth. square feetMatch them up Unpredictable numbers that are distributed over a certain range are ____.A. Random numbersB. Random equationsC. Random formulasD. Tables of formulas How many pies are there if someone eats 2 and then someone else eats 4 then I eat 13? We started with 200 pies. Andy Percifield had been busy, too. There were only two days before the next game. He was determined that his school would do the right thing, no matter what the principal said. He had an idea: maybe the students themselves could write a letter against racism that could be read over the microphone in the press box to everyone at the game. It would have to be powerful enough to satisfy the protesting players and shame the racist fans.Its Our World, Too!:Young People Who Are Making a Difference,Phillip M. HooseWhat details from the passage show why Andy wants to write a letter to be read at the game? Check all that apply.had been busy, tooonly two days before the next gameno matter what the principal saidto satisfy the protesting playersand shame the racist fans The critical resolved shear stress for a metal is 36 MPa. Determine the maximum possible yield strength (in MPa) for a single crystal of this metal that is pulled in tension. On December 31, 2019, The Bates Company's revenue is $440,000 and expenses total $340,000 before consideration of the following: Accrued wages total $21,000; Accrued revenues total $56,000; Depreciation expense is $27,000; Rental revenue of $7,000 was earned; the rent from a tenant was initially recorded by Bates as unearned rent revenue; The income tax rate is 40% of income before income taxes. What is Bates' net income after consideration of the above information An SEO account manager is concerned website developers are using too many keywords per web page. The SEO account manager would like to carry out a hypothesis test and test the claim that a web page has, on average, more than 10 keywords. Why is this hypothesis test right-tailed The sum of two consecutive numbers is 63. Find the two numbers. Wht Is a fraction equivalent to 0.4 repeating its self Que quieres aprender en esta clase? Quiere aprendo espanolQuiero aprender un poco de espanolQuerer aprende espanolQuieres aprender espanol How does the speaker describe growing up?AYou become more mature with every year.BYou carry your previous years with you.DYou are no longer intimidated by other adults someone please help thanks:) What goes in the blank?A alwaysB sometimesC neverD rarely Sodium + oxygenWhat colour is the flame produces PLEASE ANSWER THESE QUESTIONS COMPLETELY!!! WILL MARK BRAINLIEST!!!DOC 1 Questions:A. Is the suspected father actually the father of this child?B. How do you know?